Our success is based on our COMMITMENTto our customers
MILPO ANDINA PERU
Electrical and mechanical installation of the construction hoists for the “Winze 1” mine shaft, in addition to the installation of the headframe. These allow for the El Porvenir Mine deepening to level -1650m.
Construction, commissioning and startup were provided for the following: three (3) construction hoists, hoist room, galloway and headframe.